At any given time, Calderys is undertaking dozens of projects worldwide from maintenance to greenfields. Here is a selection of various projects.
| TOWN / COUNTRY |
EQUIPMENT |
YEAR |
SOLUTION |
CUSTOMER NAME |
| Galati/Romania |
BF Stack repairs: Bosch & Belly, Lower & Middle Stack, Upper Stack |
2010 |
Gunning by Robot |
Arcelor Mittal |
| Visag/India |
BF Stack repairs: Upper Stack & Armour Plates |
2010 |
Gunning by Robot |
RASHTRYIA ISPAT NIGAM VISAKHAPATNAM |
| Taranto/Italy |
Tap hole clays |
Since 2005 |
Product Solution & Delivery |
ILVA |
| Liptesk/Russia |
Tap hole clays |
Since 2005 |
Product solution & Delivery |
NMLK |
| Dunkerque/France |
Tap hole clays |
Since 1991 |
Product Solution & Delivery |
Arcelor Mittal |
| Newcastle/RSA |
BF- Runner |
Since 2006 |
Engineering, Supervision, Delivery |
Arcelor Mittal |
| Kosice/Slovakia |
BF- Runner |
Since 1998 |
Engineering, Supervision, Delivery |
US Steel |
| Enakievo/Ukrain |
BF- Runner |
Since 2002 |
Engineering, Supervision, Delivery |
EMZ |
| Raahe/Finland |
BF- Runner |
Since 1998 |
Engineering, Supervision, Delivery |
Rautaruukki |
| Scunthorpe/UK |
BF- Runner |
Since 1997 |
Full contract |
Corus |
| TOWN / COUNTRY |
EQUIPMENT |
YEAR |
SOLUTION |
CUSTOMER NAME |
| Bilaspur, India |
500 TPD Kiln |
1994 |
ACCMON 60 AF + ACCMON 45 |
Nova Iron & Steel Limited |
| Ghugus, India |
500 TPD Kiln |
1995 |
Whytheat-C Spl. |
Lloyds Metals & Egineers Ltd. |
| Champa, India |
500 TPD Kiln |
1993, 1996 |
ACCMON 80 |
Prakash Industries Limited |
| Raipur, India |
500 TPD Kiln |
1994, 2005 |
ACCMON 80+ACCMON 60+ACCMON 45 |
Raipur Alloys & Steel Limited |
| Keonjhar, India |
500 TPD Kiln |
1982 |
Whytheat-C Spl. |
Orrisa Sponge |
| Bhandara, India |
500 TPD Kiln |
1989 |
ACCMON 80 |
Sunflag Iron & Steel Co. Ltd. |
| Jharsuguda, India |
500 TPD Kiln |
2004 onwards |
ACCMON 60 A + 45 |
Bhushan Limited |
| Dhenkanal, India |
500 TPD Kiln |
|
ACCMON 60 A + 45 |
Bhushan Steel & Strips Ltd |
| Joda, India |
500 TPD Kiln |
|
|
Tata Sponge Iron Ltd |
| Raigarh, India |
500 TPD Kiln |
2004 onwards |
|
Jindal Steel & Power Limited |
| TOWN / COUNTRY |
EQUIPMENT |
YEAR |
SOLUTION |
CUSTOMER NAME |
| Steelpoort, RSA |
Ladles, Submerged Arc furnaces |
2003 - 2010 |
Full line supply |
Tubastse Ferrochrome |
| Machadodorp, RSA |
Ladles, Submerged Arc furnaces |
2003 - 2010 |
Full line supply |
Assmang Chrome |
| Meyerton, RSA |
Submerged Arc furnaces |
2003 - 2010 |
Materials & installation |
BHP Manganese |
| Brits, RSA |
Sinter Plant |
2004 |
Installation |
Hernic Ferrochrome |
| Brits, RSA |
Rotary Kiln |
2007 |
Installation |
Rovan |
| Rustenburg, RSA |
Submerged Arc furnaces |
2006 |
Install new furnace lining |
IFM |
| Rustenburg, RSA |
Submerged Arc furnace |
2010 |
Furnace rebuild |
Xstrata Wonderkop |
| Rustenburg, RSA |
Submerged Arc furnace |
2010 |
Repair Tap hole |
Xstrata Boshoek |
| Middelburg, RSA |
Sinter Plant |
2008 |
Install new furnace lining |
Middelburg Ferrochrome |
| Witbank, RSA |
Submerged Arc furnace |
2008 |
Furnace rebuild |
Transalloys |
| TOWN / COUNTRY |
EQUIPMENT |
YEAR |
SOLUTION |
CUSTOMER NAME |
| Kaohhsiung/ROC |
Ladle Refining (260t) - Bottom impact |
2010 |
Casted Monolithic Solution |
CSC |
| Donetsk/Ukrain |
Ladle Refining (125t) - Bottom & Wall |
2010 |
Casted & Gunned Monolithic Solution |
MMZ Istil |
| Dunkerque/France |
Vessel & Ladle Bottom &Wall (safety) - Low & utra low carbon Steel |
2010 |
Hot gunning repairs |
Arcelor Mittal |
| Gujurat/India |
EAF - 160 MVA/ DC (200t) - Carbon Steel |
2010 |
Hot gunning maintenance |
Essar Steel |
| Hagondange/France |
EAF - 80 MVA/ AC (120t) - Special Steel |
2010 |
Hot gunning maintenance |
Ascometal |
| Terni/Italy |
Tundish Safety+working lining & Lances |
2010 |
Cast monolithic & Maintenance patches |
AST |
| Duisburg/Germany |
Argon Lances |
2010 |
Precast |
Thyssen |
| Dunkerque/ France |
Purging plugs-SP7999 |
2010 |
Precast |
Arcelor |
| Kehl/Germany |
Purging plugs-SP8000 |
2010 |
Precast |
Badische Stahlwerke |
| Lulea/Sweden |
Lances - CAS-OB |
2010 |
Precast |
SSAB Tunnplat AB |
| TOWN / COUNTRY |
EQUIPMENT |
YEAR |
SOLUTION |
CUSTOMER NAME |
| Orissa/India |
Walking Beam Furnace: 2 new furnaces (300t/hr) |
2009 |
roof+skids |
Jindal Stainless Steel |
| GEBZE II, KOCAELI/Turkey |
Walking Beam Furnace (450t/hr) |
2010 |
|
COLAKOGLU METALURJI |
| Tornio/Finland |
Pusher Furnace (120 t/hr) |
2004 |
Revamping material+installation |
Outokumpu Stainless |
| GEBZE/Turkey |
Walking Hearth Furnace (120t/h) |
2010 |
Turnkey |
COLAKOGLU METALURJI |
| Hunedoara/Romania |
Pusher Furnace (80 t/hr) |
2010 |
Turnkey |
Arcelor Mittal |
| Isdemir/Turkey |
Pusher Furnace |
2010 |
Turnkey |
Isdemir |
| Al Jiza/Jordania |
Pusher Furnace |
2010 |
Turnkey |
UIS |
| Dunkerk/France |
Soaking Pit |
2010 |
Turnkey |
Arcelor Mittal |
| Galati/Romania |
3 Pusher Furnaces: Skids & Posts |
2010 |
Precast Solution |
Arcelor Mittal |
| Bergamo/Italia |
Rotary Kiln |
2010 |
Product Solution & Supervision |
Dalmine SPA |
| TOWN / COUNTRY |
EQUIPMENT |
YEAR |
SOLUTION |
CUSTOMER NAME |
| Sholinghur, Chennai, India |
Channel Furnace and CIF |
1995 - 2010 |
Materials |
Brakes India Limited |
| Khardaha, Kolkata, India |
Channel Furnace and CIF |
1999 - 2010 |
Materials |
Electrosteel Castings |
| Chesterfield, UK |
Channel Furnace, CIF, reciever, Ladles |
1992 - 2010 |
Materials and Installation |
UCB Ltd |
| Lohr am Main, Germany |
Cupola, Channel Furnace, Pouring Furnace, CIF, Ladles |
2000 - 2010 |
Materials |
Bosch-Rexroth |
| Skovde, Sweden |
Cupola, Channel Furnace, Pouring Furnace, Ladles |
1995 - 2010 |
Materials and Installation |
Volvo Powertrain |
| Belgium |
Channel Furnace |
1994 - 2010 |
Materials |
Proferro Leper |
| Stuttgart Germany |
Cupola, CIF, Channel Furnace, Pouring Furnace, Ladles |
1989 - 2010 |
Materials and Installation |
DAIMLER AG |
| >Yennora Sydney Australia</td>
| Cupola, CIF |
1987 - 2010 |
Materials |
Tyco Water |
| S Korea |
CIF |
1995 - 2010 |
Materials |
Metia |
| S Korea |
CIF |
1995 - 2010 |
Materials |
Sungwoo Automotive |
| tOWN / COUNTRY |
EQUIPMENT |
YEAR |
SOLUTION |
CUSTOMER NAME |
| Finspång/Sweden |
Oxy Fuel Fired Scrap Smelting Furnace |
2009 |
Compl. Relining Alkon® Cast 204 |
SAPA Heat Transfer AB |
| Finspång/Sweden |
Induction Scrap Smelting Furnace |
2007 |
Relining Alkon® Cast LC 95 |
SAPA Heat Transfer AB |
| Finspång/Sweden |
Inductors |
Yearly |
Compl. Relining Alkon® Cast 204 |
SAPA Heat Transfer AB |
| tOWN / COUNTRY |
EQUIPMENT |
YEAR |
SOLUTION |
CUSTOMER NAME |
| Slite/Sweden |
Cyclone Tower, Rotary Kiln, Cooler |
Yearly |
General Maintenance Spraycast |
Cementa AB |
| Skövde/Sweden |
Cyclone Tower, Rotary Kiln, Cooler |
Yearly |
General Maintenance LPDG |
Cementa AB |
| Värö/Sweden |
Rotary Lime Kiln, Soda Recovery Boiler, Acid Applications |
Yearly |
General Maintenance |
Södra Cell |
| Skärblacka |
Rotary Lime Kiln, Soda Recovery Boiler, Acid Applications |
2011 |
General Maintenance |
Billerud AB |
| Moss/Norway |
Rotary Lime Kiln, Soda Recovery Boiler |
Yearly |
General Maintenance |
Peterson Linerboard AS |
| Sarpsborg/Norway |
Acid Application / Lime |
Yearly |
General Maintenance |
Borregaard Industries Ltd. |
| Aspa Bruk/Sweden |
Rotary Lime Kiln, Soda Recovery Boiler |
Yearly |
General Maintenance |
Munksjö |
| Billingsfors/Sweden |
Rotary Lime Kiln, Soda Recovery Boiler |
Yearly |
General Maintenance |
Munksjö |
| Grums/Sweden |
Rotary Lime Kiln, Soda Recovery Boiler, Biomass boiler, Acid Applications |
Yearly |
General Maintenance |
Billerud AB |
| Bäckhammar/Sweden |
Rotary Lime Kiln, Soda Recovery Boiler |
Yearly |
General Maintenance |
Nordic Paper |
| Iggesund/Sweden |
Rotary Lime Kiln, Soda Recovery Boiler, Biomass boiler |
Yearly |
General Maintenance |
Iggesund Paperboard |
| Säffle/Sweden |
2 Biomass Boilers |
Yearly |
General Maintenance |
Nordic Paper |
| Vallvik/Sweden |
Rotary Lime Kiln, Soda Recovery Boiler, Biomass boiler |
Yearly |
General Maintenance |
Vallviks Bruk AB |
| Gavle/Sweden |
Rotary Lime Kiln, Soda Recovery Boiler, Biomass boiler |
Yearly |
General Maintenance |
Korsnaes AB |
| Sundsvall/sweden |
2 Biomass Boilers |
Yearly |
General Maintenance |
SCA |
| tOWN / COUNTRY |
EQUIPMENT |
YEAR |
SOLUTION |
CUSTOMER NAME |
| Norrköping/Sweden |
2 PCs Grate Boiler and 2 PCs CFB Boiler |
Yearly |
General maintenace |
Eon Värme AB |
| Linköping/Sweden |
7 PCs Grate Boiler |
Yearly |
General maintenace |
Tekniska Verken AB |
| Sogama/Spain | CFB Boiler | 2000 | Greenfield | Kvaerner AB |
| Ljungby/Sweden | Grate Boiler | 2000 | Greenfield | B&W Völund |
| Versilia/Italy | FB Boiler | 2000 | Greenfield | Kvaerner Enviro Power |
| Kiruna/Sweden | Grate boiler |
2001 | Greenfield | B&WV Aps |
| Avesta/Sweden | Grate boiler |
2002 | Greenfield | B&W Völund |
| Lidköping/Sweden | FB Boiler |
2002 | Greenfield | Kvaerner Enviro Power |
| Esbjerg/Denmark | Grate boiler |
2002 | Greenfield | B&W Völund |
| Karlstad/Sweden | Grate boiler |
2002 | Greenfield | B&W Völund |
| Kumla/Sweden | BFB Boiler |
2002 | Greenfield | Seghers BT |
| Eco Energia/Italy | FB Boiler |
2003 | Greenfield | Kvaerner Enviro Power |
| Stockholm/Sweden | Grate Boiler | 2004 | Greenfield | Babcock & Wilcox Völund |
| Uppsala/Sweden | Grate boiler | 2004 | Greenfield | Von Roll Inova |
| Fredrikstad/Norway | CFB Boiler | 2007 | Greenfield | Kvaerner AB |
| Langerbrugge/Belgium | CFB Boiler | 2009 | Greenfield | Metso Power OY |
| Ostroleka/Poland | CFB Boiler | 2010 | Greenfield | Metso Power OY |
| Norrköping/Sweden | CFB Boiler | 2010 | Greenfield | Foster & Wheeler OY |
| El Burgo/Spain | CFB Boiler | 2011 | Greenfield | Metso Power OY |
| Kumla/Sweden | Rotary kiln furnace + Grate boiler | Yearly | General maintenace | SAKAB |
| Stockholm/Sweden | 4 Grate boilers + 1 CFB | Yearly | General maintenace | Fortum - Högdalen |
| Uppsala/Sweden | 3 Grate boilers | Yearly | General maintenace | Vattenfall AB Vårme |
| Karlstad/Sweden | 1 Grate boiler | Yearly | General maintenace | Karlstad Energi AB |
| Avesta/Sweden | 1 Grate boiler | Yearly | General maintenace | Värmevärlden AB |
| Sundsvall/Sweden | 1 Grate boiler + 1 CFB Boiler | Yearly | General maintenace | Sundsvall Energi AB |
| Umeå/Sweden | 1 Grate boiler + 1 FB boiler | Yearly | General maintenace | Umeå Energi AB |
| Bollnäs/Sweden | FB Boiler |
2011 | Greenfield | Andritz |
| tOWN / COUNTRY |
EQUIPMENT |
YEAR |
SOLUTION |
CUSTOMER NAME |
| Uddevalla/Sweden |
CFB Boiler |
Yearly |
General Maintenance |
Uddevalla Kraft AB |
| Halmstad/Sweden |
Grate Boiler |
Yearly |
General Maintenance |
HEM AB |
| Falköping/Sweden |
Grate Boiler |
Yearly |
General Maintenance |
|
| Märsta/Sweden |
CFB Boiler |
Yearly |
General Maintenance |
Fortum |
| Karlstad/Sweden |
CFB Boiler |
Yearly |
General Maintenance |
Karlstad Energi |
| Fors/Sweden |
CFB Boiler |
Yearly |
General Maintenance |
Stors Enso |
| Nyköping/Sweden |
2 CFB 6 1 FB boiler |
Yearly |
General Maintenance |
Vattenfall AB Värme |
| Stockholm/Sweden |
3 Biomass boilers |
Yearly |
General Maintenance |
Fortum |
| Skellefteå/Sweden |
CFB boiler |
Yearly |
General Maintenance |
Skellefteå Kraft AB |
| Mönsterås/Sweden |
BFB Boiler | 2000 |
Greenfield |
Foster & Wheeler OY |
| Lycksele/Sweden |
CFB Boiler | 2000 |
Greenfield |
Foster & Wheeler OY |
| Mariestad/Sweden |
CFB Boiler | 2000 |
Greenfield |
Foster & Wheeler OY |
| Eskilstuna/Sweden |
FB Boiler |
2000 |
Greenfield |
Kvaerner AB |
| Örebro/Sweden |
Grate Boiler |
2001 |
Greenfield |
B&W Völund |
| Sandviken/Sweden |
2 PCs BFB Boiler |
2002 |
Greenfield |
Kvaerner AB |
| Chorzov/Poland |
2 CFB Boiler |
2002 |
Greenfield |
Foster & Wheeler OY |
| Östarsund/Sweden |
CFB Boiler |
2002 |
Greenfield |
Foster Wheeler OY |
| Narva/Estonia |
4 CFB Boilers |
2003 |
Greenfield |
Foster Wheeler OY |
| Kortileona/Italy |
FB Boiler |
2003 |
Greenfield |
Kvaerner AB |
| Kvarnsveden/Sweden |
CFB Boiler |
2004 |
Greenfield |
Foster & Wheeler OY |
| Atlon/Ireland |
2 CFB Boiler |
2004 |
Greenfield |
Foster & Wheeler OY |
| Ängelholm/Sweden |
BFB Boiler |
2005 |
Greenfield |
Kvaerner AB |
| Bergkammen/Germany |
CFB Boiler |
2005 |
Greenfield |
Foster & Wheeler OY |
| Simmeringen/Austria |
CFB Boiler |
2005 |
Greenfield |
Foster & Wheeler OY |
| Östersund/Sweden |
CFB Boiler |
2007 |
Greenfield |
Foster & Wheeler OY |
| Söderhamn/Sweden |
FB Boiler |
2007 |
Greenfield |
Austrian Energy |
| Tornio/Finland |
CFB Boiler |
2007 |
Greenfield |
Foster & Wheeler OY |
| Figueirea/Portugal |
BFB Boiler |
2008 |
Greenfield |
Metso Power OY |
| Saragossa/Spain |
CFB Boiler | 2010 |
Greenfield |
Metso Power OY |
| tOWN / COUNTRY |
EQUIPMENT |
YEAR |
SOLUTION |
CUSTOMER NAME |
| Gothenburg/Sweden |
Refinery |
2003, 2007, 2011 |
Geaneral Maintenance |
St1 AB (Shell AB) |
| Gothenburg/Sweden | Refinery | 2003, 2007, 2011 | Geaneral Maintenance | Preem AB |
| Lysekil/Sweden | Refinery | 2008, 2009, 2010 | Geaneral Maintenance | Preem AB |
| Stenungsund/Sverige | Refinery | 2008, 2009, 2010 | General Maintenance | Borealis AB |
| Nynaeshamn/Sweden | Refinery | 1993-2011 | General Maintenance | Nynaes AB |